Authors
Hua Ke, Baoding Liu
Publication date
2010/2/1
Journal
Applied Mathematical Modelling
Volume
34
Issue
2
Pages
301-308
Publisher
Elsevier
Description
Project scheduling problem is to determine the schedule of allocating resources so as to balance the total cost and the completion time. This paper considers a type of project scheduling problem with fuzzy activity duration times. According to some management goals, three types of fuzzy models are built to solve the project scheduling problem. Moreover, the technique of fuzzy simulation and genetic algorithm are integrated to design a hybrid intelligent algorithm to solve the fuzzy models. Finally, some numerical examples are given to illustrate the effectiveness of the algorithm.