Authors
Francisco Ballestín, Christoph Schwindt, Jürgen Zimmermann
Publication date
2007
Journal
International Journal of Operations Research
Volume
4
Issue
1
Pages
50-62
Description
We consider the mid-term production planning problem in make-to-order production, which consists in scheduling production orders so that the variability in the resource utilization over time is minimized. The problem is modeled as a resource leveling project scheduling problem, where production orders for final products and main components correspond to activities of a project. We present a new population-based resource leveling procedure of the iterated greedy type. The results of an experimental performance analysis including projects with up to 1000 activities indicate that the new method outperforms state-of-the-art resource leveling heuristics from literature.
Total citations
2007200820092010201120122013201420152016201720182019202020212022202320241143551037623132
Scholar articles
F Ballestín, C Schwindt, J Zimmermann - International Journal of Operations Research, 2007